  Estimated Move Date In Transit (estimated downtime) Online in MSC
Elecron Microscopy
SEM
ESEM- FEI Quanta 200 Oct. 11, 2011 (3 days) Oct. 17, 2011, Room N030K
FIB - FEI Quanta 200 3D Oct. 17, 2011 (7 days) Oct. 21, 2011, Room N031A
Hitachi S-3000H Oct. 10, 2011 (4 days) Oct. 13, 2011, Room N030A
Hitachi S-3500N Oct. 10, 2011 (4 days) Oct. 13, 2011, Room N030A
XL-20
not moving
TEM
TEM Sample Prep Nov. 29, 2011 (3 days) Dec. 19, 2011, Room N031N
JEOL 2010 F Nov. 29, 2011 (60 days)
JEOL 2010 Oct. 25, 2011 (50 days) Jan. 3, 2012, Room N030J
Philips 420 (5 days)  
 
MRL Sample Prep Nov. 7, 2011 (3 days) Nov. 17, 2011, Room N031N
 
Surface Analysis
DI AFM Oct. 7, 2011 (4 days) Oct. 17, 2011, Room N030B
Auger Nov. 17, 2011 (14 days)
XPS Nov. 7, 2011 (18 days) Jan. 13, 2012, Room N031E
Zygo - oprical profilometer Oct. 20, 2011 (1 day) Oct. 20, 2011, Room N030C
 
Particle Analysis Oct. 24, 2011 (4 days) Nov. 1, 2011, Room N004
 
Thermal Analysis Oct. 24, 2011 (4 days) Nov. 1, 2011, Room N007
 
X-ray Scattering
MRD Nov. 2, 2011 (5 days) Nov. 7, 2011, Room N008
MPD Nov. 1, 2011 (5 days) Nov. 7, 2011, Room N008
DMAX Nov. 7, 2011 (5 days) Nov. 16, 2011, Room N008
Laue Nov. 7, 2011 (7 days) Nov. 11, 2011, Room N008
Scintag 2 Nov. 7, 2011 (7 days) Nov. 15, 2011, Room N008
SAXS   not moving
 
Molecular Spectroscopy
Bruker FTIR Oct. 17, 2011 (3 days) Oct. 19, 2011, Room N007
UV-Vis-NIR Oct. 17, 2011 (2 days) Oct. 17, 2011, Room N007
Witec Raman Oct. 24, 2011 (2 days) Oct. 26, 2011, Room N007
 
Electrical Characterization TBD